Ridgefield Main Avenue Access Improvements
| Agency: | Clark County |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 2006(069) |
| Project Type: | Pedestrian & Bicycle Facilities |
| Description: | Construct new multi-modal bicycle and pedestrian facility from existing sidewalk near the Ridgefield city limits, approximately 2,200 feet north to the Carty Unit Headquarters of the Ridgefield National Wildlife Refuge. |
| Termini: | Downtown Ridgefield to Ridgefield National Wildlife Headquarters |
| Project Length: | 0.25 miles |
| Completed: | February 14, 2020 |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Construction | $148,000.00 | $4,500,000.00 | June 01, 2016 | April 13, 2017 |
| Total | $148,000.00 | $4,500,000.00 | ||