6th Street Sidewalk
| Agency: | Klickitat County |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 2020(041) |
| Project Type: | Pedestrian & Bicycle Facilities |
| Description: | Replace and construct sidewalks along 6th Street between SR-14 and Lyle Avenue. |
| Termini: | Lyle, SR-14 to Lyle Avenue |
| Project Length: | 0.10 miles |
| Completed: | April 23, 2015 |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Preliminary Engineering | $43,000.00 | July 01, 2013 | July 01, 2013 | |
| Construction | $125,000.00 | $403,300.00 | July 01, 2014 | April 22, 2014 |
| Total | $125,000.00 | $446,300.00 | ||