1st Street Pedestrian Amenities & Overlook
| Agency: | Stevenson |
|---|---|
| Status: | Under Construction |
| FHWA Aid#: | 30A2(01)) |
| Project Type: | Pedestrian & Bicycle Facilities |
| Description: | Construct pedestrian network connecting Stevenson downtown commercial core with the Columbia River waterfront. |
| Termini: | Columbia Avenue to the 2nd Street couplet |
| Project Length: | 0.20 miles |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Preliminary Engineering | $132,800.00 | $185,750.00 | July 01, 2019 | January 17, 2020 |
| Construction | $776,000.00 | $926,000.00 | September 13, 2024 | August 01, 2024 |
| Total | $908,800.00 | $1,111,750.00 | ||