NE 94th Avenue (NE Padden Parkway to NE 99th Street)
| Agency: | Clark County |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 4401(007) |
| Project Type: | Reconstruction: Add Capacity |
| Description: | Improve/construct 2-lane arterial with center turn lane/median, bike lanes, and sidewalks. Provide two travel lanes north and south (vic of NE 81st St.) continuously through Padden Parkway Intersection. Upgrade Padden/94th Street Intersection. |
| Termini: | NE Padden Parkway to NE 99th Street |
| Project Length: | 0.80 miles |
| Completed: | November 15, 2016 |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Preliminary Engineering | $200,000.00 | $909,000.00 | January 01, 2013 | February 19, 2013 |
| Right of Way | $1,478,000.00 | January 01, 2013 | January 01, 2014 | |
| Construction | $3,400,000.00 | $6,535,000.00 | January 01, 2013 | May 29, 2015 |
| Total | $3,600,000.00 | $8,922,000.00 | ||