SE 34th Street Safety & Mobility Project
| Agency: | Vancouver |
|---|---|
| Status: | Under Construction |
| Project Type: | Reconstruction: No Added Capacity |
| Description: | Repave and restripe corridor removing one travel lane in each direction. Improvements will include marked and enhanced pedestrian crossings, enhanced bicycle facilities, and ADA improvements. |
| Termini: | SE 162nd Avenue to City Limits |
| Project Length: | 1.31 miles |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Preliminary Engineering | $150,000.00 | June 01, 2023 | ||
| Construction | $1,100,000.00 | $1,780,000.00 | September 15, 2024 | September 16, 2024 |
| Total | $1,100,000.00 | $1,930,000.00 | ||