Pioneer Street Railroad Overpass
| Agency: | Port of Ridgefield |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 7071(002) |
| Project Type: | New Construction Roadway |
| Description: | Construction of rail overpass to provide safer, unobstructed, direct access from downtown Ridgefield to the Port of Ridgefield. |
| Termini: | Pioneer/Main across BNSF tracks |
| Project Length: | 0.34 miles |
| Completed: | September 30, 2021 |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Preliminary Engineering | $2,160,000.00 | July 01, 2005 | July 01, 2005 | |
| Right of Way | $749,000.00 | July 01, 2011 | July 01, 2011 | |
| Construction | $2,000,000.00 | $14,179,000.00 | June 01, 2016 | October 18, 2019 |
| Total | $2,000,000.00 | $17,088,000.00 | ||
Project Documents
| Project Showcase Flyer (PDF 673 KB) |