Highway 99 Pedestrian/Bicycle Improvements
| Agency: | Clark County |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 4253(014) |
| Project Type: | Pedestrian & Bicycle Facilities |
| Description: | Construct and widen sidewalk, remove or adjust utilities, ADA and APS upgrades, add midblock pedestrian crossing and HAWK signal, enhance bike lane striping. Transit stop relocation or upgrades. |
| Termini: | NE 63rd St. to NE 78th St. |
| Project Length: | 0.75 miles |
| Completed: | December 31, 2017 |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Preliminary Engineering | $150,000.00 | $355,000.00 | July 01, 2015 | March 17, 2016 |
| Right of Way | $583,000.00 | January 01, 2016 | March 17, 2016 | |
| Construction | $400,000.00 | $1,479,000.00 | August 15, 2016 | April 24, 2017 |
| Total | $550,000.00 | $2,417,000.00 | ||
Project Documents
| Project Showcase Flyer (PDF 81 KB) |
| Before After Report (PDF 5 MB) |