Highway 99 Traffic Signal Optimization
| Agency: | Clark County |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 0099(116) |
| Project Type: | TSMO |
| Description: | Signal hardware, interconnection and coordination of signal operation along corridor. Repair/upgrades to traffic detection. Addition of video cameras and permanent count stations at key locations. Connection of signal equipment to central county monitoring center. |
| Termini: | Ross St. to NE 117th Av. |
| Project Length: | 3.20 miles |
| Completed: | September 30, 2014 |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Preliminary Engineering | $92,000.00 | $112,000.00 | February 01, 2011 | February 03, 2011 |
| Construction | $1,254,000.00 | $1,454,000.00 | January 01, 2012 | May 10, 2013 |
| Total | $1,346,000.00 | $1,566,000.00 | ||
List of all projects.