Evergreen Way/32nd Street Improvements
| Agency: | Washougal |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 7071(002) |
| Project Type: | Reconstruction: No Added Capacity |
| Description: | Reconstruct intersection at Evergreen and 32nd Street, including new signal, widened thru and turn lanes, new bike lanes, and pedestrian facilities. |
| Termini: | Evergreen at 32nd Street |
| Project Length: | 0.10 miles |
| Completed: | July 15, 2018 |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Preliminary Engineering | $63,000.00 | $230,000.00 | January 15, 2012 | July 05, 2012 |
| Right of Way | $129,000.00 | May 15, 2012 | October 01, 2015 | |
| Construction | $937,000.00 | $1,490,000.00 | December 30, 2014 | June 05, 2017 |
| Total | $1,000,000.00 | $1,849,000.00 | ||