SR-503 Traveler Information - Incident Management and Communications
| Agency: | WSDOT-SW |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 4503(013) |
| Project Type: | TSMO |
| Description: | Complete fiber communications system and deploy advanced traveler information system. |
| Termini: | MP 0.0 to 8.2 |
| Project Length: | 7.98 miles |
| Completed: | March 01, 2016 |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Preliminary Engineering | $60,000.00 | $80,000.00 | February 01, 2012 | April 13, 2014 |
| Construction | $699,000.00 | $920,000.00 | January 01, 2013 | January 31, 2014 |
| Total | $759,000.00 | $1,000,000.00 | ||
Project Documents
| Project Showcase Flyer (PDF 119 KB) |
| Before After Report (PDF 272 KB) |