Signal Timing, Evaluation, Verification and Enhancement
| Agency: | Clark County |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 9906(046) |
| Project Type: | TSMO |
| Description: | Install Intelligent Transportation System (ITS) devices, collect and analyze data in real-time. |
| Termini: | Padden Parkway, Highway 99, NE 99th Street, 139th Street, and Tenney Road |
| Project Length: | 15.20 miles |
| Completed: | December 15, 2019 |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Preliminary Engineering | $360,000.00 | $400,000.00 | April 01, 2015 | April 17, 2015 |
| Construction | $684,600.00 | $889,374.00 | January 01, 2016 | November 21, 2017 |
| Total | $1,044,600.00 | $1,289,374.00 | ||
Project Documents
| Project Showcase Flyer (PDF 375 KB) |
| Before After Report (PDF 469 KB) |