NE 99th Street
| Agency: | Clark County |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 4410(004) |
| Project Type: | New Construction Roadway |
| Description: | Reconstruct existing roadway to arterial standard matching up to existing improvements at SR-503. Extend missing segment of roadway across the landfill to meet NE 94th Avenue. |
| Termini: | NE 94th Avenue to NE 117th Avenue |
| Project Length: | 1.10 miles |
| Completed: | December 15, 2023 |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Preliminary Engineering | $150,000.00 | $1,210,000.00 | January 01, 2020 | September 04, 2019 |
| Right of Way | $3,700,000.00 | January 01, 2021 | October 06, 2020 | |
| Construction | $10,300,000.00 | $25,099,000.00 | September 15, 2022 | August 03, 2022 |
| Total | $10,450,000.00 | $30,009,000.00 | ||
List of all projects.