Gee Creek Trail-Abrams Park to Heron Drive
| Agency: | Ridgefield |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 1085(006) |
| Project Type: | Pedestrian & Bicycle Facilities |
| Description: | Construct pedestrian and bicycle trail between Abrams Park and Heron Drive. |
| Termini: | Abrams Park to Heron Drive |
| Project Length: | 0.40 miles |
| Completed: | December 31, 2021 |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Construction | $88,458.00 | $102,264.00 | January 01, 2020 | December 15, 2020 |
| Total | $88,458.00 | $102,264.00 | ||
Project Documents
| Project Showcase Flyer (PDF 381 KB) |