Project Showcase
Projects
Project Showcase
Scroll horizontally, if needed to see more columns
NW Neighborhood Connectivity Improvements
| Agency: | Vancouver |
|---|---|
| Status: | Design |
| FHWA Aid#: | 1350(028) |
| Project Type: | Pedestrian & Bicycle Facilities |
| Description: | Construct sidewalk/ath in the vicinity of Lincoln Avenue and NW 53rd Street. Construct shared bicycle facility along Grant Avenue, NW 43rd Street, and Lincoln Avenue Avenue in the vicinity of Lincoln Elementary School. |
| Termini: | NW 43rd St. to NW 53rd St. |
| Project Length: | 0.75 miles |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Preliminary Engineering | $145,000.00 | $382,966.00 | January 01, 2019 | August 14, 2018 |
| Right of Way | $112,961.00 | January 01, 2020 | August 01, 2020 | |
| Construction | $1,834,579.00 | January 01, 2022 | August 01, 2021 | |
| Total | $145,000.00 | $2,330,506.00 | ||
List of all projects.