Project Showcase
Projects
Project Showcase
Scroll horizontally, if needed to see more columns
SR-502/SR-503 Intersection Improvements
| Agency: | Battle Ground |
|---|---|
| Status: | Completed |
| FHWA Aid#: | CNWA(010) |
| Project Type: | Reconstruction: No Added Capacity |
| Description: | Add right turn lanes, dual left turn lanes, and pork chop islands for pedestrian safety. |
| Termini: | |
| Completed: | November 30, 2023 |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Preliminary Engineering | $600,000.00 | August 15, 2017 | August 15, 2017 | |
| Right of Way | $185,000.00 | January 15, 2020 | January 15, 2020 | |
| Construction | $4,091,688.00 | $4,567,538.00 | October 15, 2022 | August 31, 2022 |
| Total | $4,091,688.00 | $5,352,538.00 | ||
Project Documents
| Project Showcase Flyer (PDF 207 KB) |
List of all projects.