NW 38th Avenue
| Agency: | Camas |
|---|---|
| Status: | Under Construction |
| FHWA Aid#: | 7031(004) |
| Project Type: | Reconstruction: No Added Capacity |
| Description: | Improve to 3-lane minor arterial standards with bike lanes and sidewalks. |
| Termini: | NW Parker Street to Grass Valley Park |
| Project Length: | 0.45 miles |
| Phase | Federal Funds | Project Cost | Schedule | Obligation |
|---|---|---|---|---|
| Preliminary Engineering | $335,700.00 | $680,000.00 | January 15, 2022 | July 24, 2020 |
| Right of Way | $213,100.00 | $813,000.00 | July 01, 2022 | June 09, 2022 |
| Construction | $5,758,400.00 | $9,203,940.00 | September 13, 2024 | August 01, 2024 |
| Total | $6,307,200.00 | $10,696,940.00 | ||