NW 38th Avenue/SE 20th Street, Phase 2

Agency: Camas
Status: Completed
FHWA Aid#: 7031(003)
Project Type: Reconstruction: Add Capacity
Description: Improve to urban road standards with three lanes, bike lanes, sidewalks, storm systems, illumination, and utilities.
Termini: SE Armstrong Street to NW Parker Street
Project Length: 0.55 miles
Completed: March 31, 2016
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $480,000 June 1, 2012 June 1, 2012
Right of Way $1,670,000 June 1, 2013 June 1, 2013
Construction $2,200,000 $4,730,000 March 1, 2014 April 7, 2014
Total $2,200,000 $6,880,000    