Southwest Washington Regional Transportation Council

Project Showcase

Highway 99 Traffic Responsive Incident Management

Agency: Clark County
Status: Completed
FHWA Aid#: 0099(133)
Project Type: Transportation System Management and Operations
Description: Upgrade central traffic control hardware and software to enable automatic rules-based detection of changing traffic volumes and congestion. Consultant will develop rules and update/audit of fiber-optic inventory in OSP InSight software to reflect as-built network
Termini: Ross Rd. to NE 134th St.
Project Length: 7.20 miles
Completed: October 1, 2015
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $420,000 $539,000 December 1, 2014 October 17, 2014
Total $420,000 $539,000    

Project Documents

Project Photos

  • Project Location