Transit Signal Priority-Highway 99

Agency: C-TRAN
Status: Completed
FHWA Aid#: FT14(004)
Project Type: Transportation System Management and Operations
Description: Install and operate Transit Signal Priority at intersections along Highway 99 from Ross Street to the 99th Street Transit Center to include intersections west of Hwy 99 on 99th Street and south on 7th Avenue.
Termini: Ross Street to 7th Avenue
Project Length: 2.70 miles
Completed: March 30, 2021
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $120,000 $150,000 October 1, 2014 May 15, 2014
Construction $20,000 $25,000 March 1, 2015 May 15, 2014
Total $140,000 $175,000    