Southwest Washington Regional Transportation Council

Project Showcase

Pioneer Street Railroad Overpass

Agency: Port of Ridgefield
Status: Completed
FHWA Aid#: 7071(002)
Project Type: New Construction Roadway
Description: Construction of rail overpass to provide safer, unobstructed, direct access from downtown Ridgefield to the Port of Ridgefield.
Termini: Pioneer/Main across BNSF tracks
Project Length: 0.34 miles
Completed: September 30, 2021
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $2,160,000 July 1, 2005 July 1, 2005
Right of Way $749,000 July 1, 2011 July 1, 2011
Construction $2,000,000 $14,179,000 June 1, 2016 October 18, 2019
Total $2,000,000 $17,088,000    