Southwest Washington Regional Transportation Council

Project Showcase

NW 18th Avenue Bike and Pedestrian Trail

Agency: Camas
Status: Completed
FHWA Aid#: 7034(002)
Project Type: Pedestrian & Bicycle Facilities
Description: The project completes a vital pedestrian and bike link on the south side of NW 18th Avenue from NW Beech Street to SE 201st Avenue. This trail improves access from approximately1,000 households to Prune Hill Sports Park and Prune Hill Elementary School to the east and retail and medical facilities to the west. This project completes a continuous pedestrian link to 192nd Avenue corridor.
Termini: NW Beech Street to SE 201st Avenue
Project Length: 0.33 miles
Completed: March 15, 2015
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $20,000 $24,800 October 1, 2013 March 21, 2014
Right of Way $125,000 December 1, 2013 February 28, 2014
Construction $200,000 $250,500 July 1, 2014 July 11, 2014
Total $220,000 $400,300    