Highway 99 Traffic Signal Optimization
Agency: | Clark County |
---|---|
Status: | Completed |
FHWA Aid#: | 0099(116) |
Project Type: | Transportation System Management and Operations |
Description: | Signal hardware, interconnection and coordination of signal operation along corridor. Repair/upgrades to traffic detection. Addition of video cameras and permanent count stations at key locations. Connection of signal equipment to central county monitoring center. |
Termini: | Ross St. to NE 117th Av. |
Project Length: | 3.20 miles |
Completed: | September 30, 2014 |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Preliminary Engineering | $92,000 | $112,000 | February 1, 2011 | February 3, 2011 |
Construction | $1,254,000 | $1,454,000 | January 1, 2012 | May 10, 2013 |
Total | $1,346,000 | $1,566,000 |