Mill Plain TSP Phase II
Agency: | C-TRAN |
---|---|
Status: | Completed |
FHWA Aid#: | FT19(002) |
Project Type: | Transportation System Management and Operations |
Description: | Implement traffic signal priority on remaining intersections along Mill Plain and 164th Av. |
Termini: | I-5 to 182nd Avenue |
Project Length: | 9.30 miles |
Completed: | October 1, 2023 |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Construction | $195,500 | $262,500 | February 1, 2018 | May 3, 2019 |
Total | $195,500 | $262,500 |