Fourth Plain Subarea Sidewalk Infill Project

Agency: Vancouver
Status: Completed
FHWA Aid#: 9906(041)
Project Type: Pedestrian & Bicycle Facilities
Description: Improve pedestrian facilities along Neals Lane and Rossiter Lane in the vicinity of Fourth Plain Boulevard.
Termini: Fourth Plain Blvd. to 27th St.
Project Length: 0.50 miles
Completed: March 22, 2018
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $96,300 $111,300 January 1, 2013 May 7, 2013
Right of Way $323,600 $374,100 January 1, 2014 October 20, 2014
Construction $480,300 $639,300 January 1, 2015 February 21, 2017
Total $900,200 $1,124,700    