Project Showcase
Mill Plain Boulevard Arrival on Green Improvement Project
Agency: | Vancouver |
---|---|
Status: | Completed |
FHWA Aid#: | 4242(027) |
Project Type: | Transportation System Management and Operations |
Description: | Install signal equipment at multiple signalized intersections along Mill Plain to improve signal coordination along the corridor. |
Termini: | Andresen Road to 155th Av. |
Project Length: | 4.30 miles |
Completed: | July 12, 2021 |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Construction | $72,700 | $97,600 | February 1, 2017 | August 12, 2020 |
Total | $72,700 | $97,600 |