SE 1st Street, 162nd Av. to 177th Av.
Agency: | Vancouver |
---|---|
Status: | Completed |
FHWA Aid#: | 4266(002) |
Project Type: | Reconstruction: Add Capacity |
Description: | Widen to 3 lanes with sidewalk and bicycle lanes. |
Termini: | 162nd Av. to 177th Av. |
Project Length: | 1.00 miles |
Completed: | December 31, 2023 |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Preliminary Engineering | $600,000 | $2,100,000 | June 1, 2009 | July 1, 2009 |
Right of Way | $1,000,000 | $1,500,000 | January 1, 2012 | January 9, 2015 |
Construction | $7,203,151 | $11,424,951 | September 15, 2022 | July 14, 2022 |
Total | $8,803,151 | $15,024,951 |