SE 1st Street, 162nd Av. to 177th Av.

Agency: Vancouver
Status: Completed
FHWA Aid#: 4266(002)
Project Type: Reconstruction: Add Capacity
Description: Widen to 3 lanes with sidewalk and bicycle lanes.
Termini: 162nd Av. to 177th Av.
Project Length: 1.00 miles
Completed: December 31, 2023
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $600,000 $2,100,000 June 1, 2009 July 1, 2009
Right of Way $1,000,000 $1,500,000 January 1, 2012 January 9, 2015
Construction $7,203,151 $11,424,951 September 15, 2022 July 14, 2022
Total $8,803,151 $15,024,951    