Project Showcase
Evergreen Highway Trail
Agency: | Vancouver |
---|---|
Status: | Completed |
FHWA Aid#: | 4228(001) |
Project Type: | Pedestrian & Bicycle Facilities |
Description: | Build bike and pedetrian trail along Evergreen Highway. |
Termini: | Ellsworth to Weber Arboretum |
Project Length: | 0.87 miles |
Completed: | October 15, 2015 |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Preliminary Engineering | $138,750 | $138,750 | September 1, 2010 | January 19, 2012 |
Right of Way | $125,000 | $125,000 | February 1, 2011 | December 17, 2013 |
Construction | $661,250 | $661,250 | September 1, 2011 | February 25, 2015 |
Total | $925,000 | $925,000 |
Project Photos
List of all projects.