Southwest Washington Regional Transportation Council

Project Showcase

2010 Sidewalk Enhancement Project

Agency: Clark County
Status: Completed
FHWA Aid#: 2006(059)
Project Type: Pedestrian & Bicycle Facilities
Description: Construct concrete curb and sidewalk along 94th St., NW 1st Av., and 72nd Av.
Termini: Various
Project Length: 0.12 miles
Completed: May 22, 2013
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $45,000 $45,000 July 15, 2009 August 12, 2010
Right of Way $15,000 July 15, 2009 January 1, 2010
Construction $245,000 $245,000 November 1, 2010 September 1, 2011
Total $290,000 $305,000    

Project Photos