Southwest Washington Regional Transportation Council

Project Showcase

Evergreen Trail

Agency: Vancouver
Status: Design
FHWA Aid#: 4228(002)
Project Type: Pedestrian & Bicycle Facilities
Description: Build pervious asphalt path along Evergreen Highway.
Termini: Chelsea Av. to Image Rd.
Project Length: 1.10 miles
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $100,000 $175,000 June 1, 2014 September 8, 2014
Right of Way $65,000 January 1, 2016
Construction $960,000 December 1, 2017
Total $100,000 $1,200,000    

List of all projects.