Project Showcase
Evergreen Trail
Agency: | Vancouver |
---|---|
Status: | Under Construction |
FHWA Aid#: | 4228(002) |
Project Type: | Pedestrian & Bicycle Facilities |
Description: | Build pervious asphalt path along Evergreen Highway. |
Termini: | Chelsea Av. to Image Rd. |
Project Length: | 1.10 miles |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Preliminary Engineering | $100,000 | $280,000 | June 1, 2014 | September 8, 2014 |
Right of Way | $350,000 | January 1, 2016 | March 1, 2020 | |
Construction | $500,000 | $2,341,500 | June 1, 2023 | |
Total | $600,000 | $2,971,500 |