SE Grace Avenue, Main to Rasmussen
Agency: | Battle Ground |
---|---|
Status: | Design |
Project Type: | Reconstruction: No Added Capacity |
Description: | Realign and widen to three lane facility, add sidewalks, storm drainage, striping, lighting, landscaping, and bike facilities. Make some sewer and water improvements. Add traffic signal at realigned Main and Grace intersection. |
Termini: | Main to Rasmussen |
Project Length: | 0.50 miles |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Preliminary Engineering | $744,188 | August 1, 2019 | July 14, 2020 | |
Right of Way | $1,544,500 | January 1, 2024 | ||
Construction | $2,300,000 | $5,100,000 | June 1, 2026 | |
Total | $2,300,000 | $7,388,688 |