Project Showcase
SR-502/SR-503 Intersection Improvements
Agency: | Battle Ground |
---|---|
Status: | Completed |
FHWA Aid#: | CNWA(010) |
Project Type: | Reconstruction: No Added Capacity |
Description: | Add right turn lanes, dual left turn lanes, and pork chop islands for pedestrian safety. |
Termini: | |
Completed: | November 30, 2023 |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Preliminary Engineering | $600,000 | August 15, 2017 | August 15, 2017 | |
Right of Way | $185,000 | January 15, 2020 | January 15, 2020 | |
Construction | $4,091,688 | $4,567,538 | September 15, 2022 | August 31, 2022 |
Total | $4,091,688 | $5,352,538 |