Southwest Washington Regional Transportation Council

Project Showcase

NW 38th Avenue

Agency: Camas
Status: Grant Approved
Project Type: Reconstruction: No Added Capacity
Description: Improve to 3-lane minor arterial standards with bike lanes and sidewalks.
Termini: NW Parker Street to Grass Valley Park
Project Length: 0.45 miles
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $335,700 $1,015,700 January 15, 2022
Right of Way $477,900 $1,290,900 January 15, 2023
Construction $3,399,300 March 15, 2024
Total $813,600 $5,705,900    