Project Showcase
NW 38th Avenue
Agency: | Camas |
---|---|
Status: | Under Construction |
FHWA Aid#: | 7031(004) |
Project Type: | Reconstruction: No Added Capacity |
Description: | Improve to 3-lane minor arterial standards with bike lanes and sidewalks. |
Termini: | NW Parker Street to Grass Valley Park |
Project Length: | 0.45 miles |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Preliminary Engineering | $335,700 | $680,000 | January 15, 2022 | July 24, 2020 |
Right of Way | $213,100 | $813,000 | July 1, 2022 | June 9, 2022 |
Construction | $5,758,400 | $9,203,940 | September 13, 2024 | August 1, 2024 |
Total | $6,307,200 | $10,696,940 |