Southwest Washington Regional Transportation Council

Project Showcase

Trail of the Gods

Agency: Stevenson
Status: Completed
FHWA Aid#: WA11(002)
Project Type: Pedestrian & Bicycle Facilities
Description: Extends City of Stevenson's mutli-use trail system to its western city limit.
Termini: Stevenson, Rock Creek Rd. to Mallicott Rd.
Project Length: 0.45 miles
Completed: May 14, 2015
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $131,600 July 1, 2011 July 1, 2011
Construction $66,400 $773,100 July 1, 2013 May 21, 2014
Total $66,400 $904,700    