Project Showcase
Trail of the Gods
Agency: | Stevenson |
---|---|
Status: | Completed |
FHWA Aid#: | WA11(002) |
Project Type: | Pedestrian & Bicycle Facilities |
Description: | Extends City of Stevenson's mutli-use trail system to its western city limit. |
Termini: | Stevenson, Rock Creek Rd. to Mallicott Rd. |
Project Length: | 0.45 miles |
Completed: | May 14, 2015 |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Preliminary Engineering | $131,600 | July 1, 2011 | July 1, 2011 | |
Construction | $66,400 | $773,100 | July 1, 2013 | May 21, 2014 |
Total | $66,400 | $904,700 |