Southwest Washington Regional Transportation Council

Project Showcase

1st Street Pedestrian Amenities & Overlook

Agency: Stevenson
Status: Under Construction
FHWA Aid#:
Project Type: Pedestrian & Bicycle Facilities
Description: Construct pedestrian network connecting Stevenson downtown commercial core with the Columbia River waterfront.
Termini: Columbia Avenue to the 2nd Street couplet
Project Length: 0.20 miles
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $132,800 $185,750 July 1, 2019 January 17, 2020
Construction $776,000 $926,000 September 13, 2024 August 1, 2024
Total $908,800 $1,111,750    

Project Photos

  • Map
  • Before Looking North
  • Before Looking East
  • Looking up from waterfront