SR 500/Everett Street

Agency: Camas
Status: Programmed
Project Type: Reconstruction: No Added Capacity
Description: Improve to urban standards with sidewalks, bike lanes, illumination and stormwater facilities.
Termini: NE 35th Avenue to NE 43rd Avenue
Project Length: 0.50 miles
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $375,000 $1,100,000 June 1, 2026
Right of Way $3,000,000 June 1, 2027
Construction $10,410,000 June 1, 2028
Total $375,000 $14,510,000    