Southwest Washington Regional Transportation Council

Project Showcase

NE 99th Street

Agency: Clark County
Status: Completed
FHWA Aid#: 4410(004)
Project Type: New Construction Roadway
Description: Reconstruct existing roadway to arterial standard matching up to existing improvements at SR-503. Extend missing segment of roadway across the landfill to meet NE 94th Avenue.
Termini: NE 94th Avenue to NE 117th Avenue
Project Length: 1.10 miles
Completed: December 15, 2023
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $150,000 $1,210,000 January 1, 2020 September 4, 2019
Right of Way $3,700,000 January 1, 2021 October 6, 2020
Construction $10,300,000 $25,099,000 September 15, 2022 August 3, 2022
Total $10,450,000 $30,009,000    