NE 10th Avenue, NE 149th St. -NE 154th St
Agency: | Clark County |
---|---|
Status: | Completed |
FHWA Aid#: | 4201(003) |
Project Type: | Reconstruction: No Added Capacity |
Description: | Improve to 3-lane urban standards, with bike lanes and sidewalks. |
Termini: | NE 149th Street to NE 154th Street |
Project Length: | 0.25 miles |
Completed: | July 27, 2022 |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Preliminary Engineering | $1,579,000 | January 15, 2017 | January 15, 2017 | |
Right of Way | $1,398,000 | January 15, 2019 | January 15, 2019 | |
Construction | $3,000,000 | $10,557,000 | April 15, 2020 | August 7, 2020 |
Total | $3,000,000 | $13,534,000 |